FM 1103 Utility Relocations

Before TxDOT can release the FM 1103 expansion project for construction, the City of Schertz must relocate the existing water and wastewater lines that are in conflict with the planned roadway and drainage improvements. The utility relocation project was awarded to D. Guerra Construction on April 9th and the Notice to Proceed was issued on July 29th.  Construction began in August.

Construction Start: August 2019
Construction Completion: Summer 2020
Cost of Construction: $900,000.00
Funding Source: CO 2018 Bond

UPDATE -  June 2020

  • Removal and abandonment of the old water and wastewater mains is complete.
  • Site restoration and clean up continues throughout the project.
  1. Scott McClelland, P.E.

    Engineer
    Phone: 210-619-1822

FM 1103 Utility Relocations Location Map

Progress Photos

Sewer Casing_01_041620
WIN_20200406_13_50_26_Pro
WIN_20200402_14_10_00_Pro