FM 1103 Utility Relocations

Before TxDOT can release the FM 1103 expansion project for construction, the City of Schertz must relocate the existing water and wastewater lines that are in conflict with the planned roadway and drainage improvements. The utility relocation project was awarded to D. Guerra Construction on April 9th and the Notice to Proceed was issued on July 29th.  Construction is expected to begin in August.

Construction Start: August 2019
Construction Completion: January 2020
Cost of Construction: $900,000.00
Funding Source: CO 2018 Bond

UPDATE -  August 2019

  • Stormwater BMPs (best management practices) were installed throughout the entire project.
  • The bore across F.M. 1103 near the IH-35 Frontage Road for the waterline relocation is complete.
  1. Scott McClelland, E.I.T.

    Project Manager
    Phone: 210-619-1822

FM 1103 Utility Relocations Location Map