FM 1103 Utility Relocations

Before TxDOT can release the FM 1103 expansion project for construction, the City of Schertz must relocate the existing water and wastewater lines that are in conflict with the planned roadway and drainage improvements. The utility relocation project was awarded to D. Guerra Construction on April 9th and the Notice to Proceed was issued on July 29th.  Construction began in August.

Construction Start: August 2019
Construction Completion: January 2020
Cost of Construction: $900,000.00
Funding Source: CO 2018 Bond

UPDATE -  October 2019

  • Installation of the third section of waterline relocation was completed near FM 1103 and Fortune Hill. 
  • In total, approximately 1,300 feet of waterline has been installed.
  1. Scott McClelland, E.I.T.

    Project Manager
    Phone: 210-619-1822

FM 1103 Utility Relocations Location Map

Progress Photos

fm1103 tie in
WIN_20191007_13_52_06_Pro
untitled