FM 1103 Utility Relocations

Before TxDOT can release the FM 1103 expansion project for construction, the City of Schertz must relocate the existing water and wastewater lines that are in conflict with the planned roadway and drainage improvements.

Phase I of the utility relocation project was awarded to D. Guerra Construction on April 9th, 2019 and the Notice to Proceed was issued on July 29th, 2019. Construction began in August 2019 and was substantially complete in May of 2020. 

Construction Start: August 2019
Construction Completion: June 2020
Council Approved Construction Budget: $980,099.22
Final Construction Contract Amount: $931,702.87
Funding Source: CO 2018 Bond

Phase II of the utility relocation project was awarded to M&C Fonseca Construction on August 11th, 2020. The Notice to Proceed was issued for September 14, 2020 which is also the date the contractor plans to mobilize and being work. Phase II of the project is slated to take approximately 60 days to complete.

Construction Start: September 14, 2020
Estimated Construction Completion: November 2020
Council Approved Construction Budget: $143,312.00
Final Construction Contract Amount:
Funding Source: CO 2018 Bond
  1. Larry Busch Jr., E.I.T.

    Senior Graduate Engineer
    Phone: 210-619-1802

FM 1103 Utility Relocations Location Map

Progress Photos

Sewer Casing_01_041620
WIN_20200406_13_50_26_Pro
WIN_20200402_14_10_00_Pro