FM 1103 Utility Relocations

Before TxDOT can release the FM 1103 expansion project for construction, the City of Schertz must relocate the existing water and wastewater lines that are in conflict with the planned roadway and drainage improvements. The utility relocation project was awarded to D. Guerra Construction on April 9th and the Notice to Proceed was issued on July 29th.  Construction began in August.

Construction Start: August 2019
Construction Completion: Spring 2020
Cost of Construction: $900,000.00
Funding Source: CO 2018 Bond

UPDATE -  february 2020

  • Work began installing the realigned sewer main at the corner of IH-35 and FM 1103.
  • Site restoration began on the Wiederstein Road end of the project.
  • The contractor plans to complete the remaining sewer realignment work in March.
  1. Scott McClelland, P.E.

    Project Manager
    Phone: 210-619-1822

FM 1103 Utility Relocations Location Map

Progress Photos

20200227_151220
20200227_151455